Docket NumberProject NameDescriptionCreated Status
23-392Dooley's Natural Gas II, LLC (Dooley's) is proposing to construct approximately 28 miles of 4-inch and 2-inch pipeline in Chippewa, Swift, and Kandiyohi Counties10/06/2023 02:36 PM
23-109The Magellan Pipeline Company proposes to relocate approximately 0.74 miles of an existing petroleum pipeline in Pipestone County. 04/13/2023 01:58 PM
23-43Heartland Corn Products proposes to construct an approximately 7.78-mile long, 6.625-inch outside diameter natural gas pipeline in Sibley County, Minnesota. The pipeline will originate near 595th Avenue, north of Highway MN- 19 (west of the City of Winthrop) and tie into the Hutchinson Utilities Commission pipeline at a new interconnect station. 03/20/2023 04:02 PM
  • 2023-03-20: Docket is open
  • :
22-422Summit Carbon Solutions, LLC, proposes to construct about 30 miles of carbon dioxide pipeline through Otter Tail and Wilkin Counties.10/27/2022 03:04 PM
21-266BP Midwest Product Pipelines Holding, LLC (BPMW) is proposing to reroute a section of pipeline near the Rochester International Airport in Olmsted County, Minnesota. 03/31/2022 11:57 AM
20-872Petroleum Fuels Company (PFC) is proposing to construct a 5,600 foot long natural gas pipeline in Dakota County. The pipeline will transport natural gas from a processing facility near the Pine Bend landfill to an interconnection with the Northern States Power gas system.12/31/2020 12:59 PM
  • 2021-02-23: Application accepted
  • 2021-03-25: Public meeting
  • 2021-07-07: Permit issued
  • : Project built
  • : Docket closed
18-752Enbridge Energy, Limited Partnership has applied for a Pipeline Route Permit and Partial Exemption for the Fond du Lac Line 4 Project on the Fond du Lac Band of Lake Superior Chippewa Reservation. The Project will relocate approximately 10 miles of the existing Line 4 pipeline from the center to the outer edge of the existing Enbridge Mainline Corridor within the Fond du Lac Band Reservation. 03/04/2019 11:22 AM
  • 2019-02-25: Docket is open
  • 2019-04-11: Application accepted
  • 2019-05-22: Public meeting
  • 2019-06-28: ALJ report issued
  • : Permit Decision
  • : Project built
  • : Project Closed
15-858Minnesota Energy Resources Corporation is proposing to install approximately 13.1 miles of new natural gas pipeline west and south of the city of Rochester in Olmsted County, Minnesota11/03/2015 12:00 AM
  • 2016-02-03: Application accepted
  • 2016-02-29: Public meeting
  • 2016-07-26: Routes accepted for consideration
  • 2016-09-16: Environmental document available
  • Upcoming: Public hearing
  • Upcoming: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed
15-137Enbridge Energy proposes to replace 337 miles of the Line 3 Pipeline in Minnesota. Line 3 originates in Canada, continues through North Dakota, enters Minnesota in Kittson County, and terminates in Superior, Wiscsonsin. 02/23/2015 12:00 AM
  • 2015-07-01: Application accepted
  • 2016-04-25: Public meeting
  • 2016-12-05: Scoping decision
  • 2017-05-15: Draft EIS available
  • 2017-09-26: Public hearing
  • 2018-02-02: Final EIS available
  • 2018-04-24: ALJ report issued
  • 2018-10-26: Permit issued
  • Upcoming: Project built
  • Upcoming: Docket closed