23-392 | | Dooley's Natural Gas II, LLC (Dooley's) is proposing to construct approximately 28 miles of 4-inch and 2-inch pipeline in Chippewa, Swift, and Kandiyohi Counties | 10/06/2023 02:36 PM | |
23-109 | | The Magellan Pipeline Company proposes to relocate approximately 0.74 miles of an existing petroleum pipeline in Pipestone County.
| 04/13/2023 01:58 PM | |
23-43 | | Heartland Corn Products proposes to construct an approximately 7.78-mile long, 6.625-inch outside diameter natural gas pipeline in Sibley County, Minnesota. The pipeline will originate near 595th Avenue, north of Highway MN- 19 (west of the City of Winthrop) and tie into the Hutchinson Utilities Commission pipeline at a new interconnect station. | 03/20/2023 04:02 PM |
View All...
-
2023-03-20: Docket is open
-
:
|
22-422 | | Summit Carbon Solutions, LLC, proposes to construct about 30 miles of carbon dioxide pipeline through Otter Tail and Wilkin Counties. | 10/27/2022 03:04 PM | |
21-266 | | BP Midwest Product Pipelines Holding, LLC (BPMW) is proposing to reroute a section of pipeline near the Rochester International Airport in Olmsted County, Minnesota. | 03/31/2022 11:57 AM | |
20-872 | | Petroleum Fuels Company (PFC) is proposing to construct a 5,600 foot long natural gas pipeline in Dakota County. The pipeline will transport natural gas from a processing facility near the Pine Bend landfill to an interconnection with the Northern States Power gas system. | 12/31/2020 12:59 PM |
View All...
-
2021-02-23: Application accepted
-
2021-03-25: Public meeting
-
2021-07-07: Permit issued
-
: Project built
-
: Docket closed
|
18-752 | | Enbridge Energy, Limited Partnership has applied for a Pipeline Route Permit and Partial Exemption for the Fond du Lac Line 4 Project on the Fond du Lac Band of Lake Superior Chippewa Reservation. The Project will relocate approximately 10 miles of the existing Line 4 pipeline from the center to the outer edge of the existing Enbridge Mainline Corridor within the Fond du Lac Band Reservation. | 03/04/2019 11:22 AM |
View All...
-
2019-02-25: Docket is open
-
2019-04-11: Application accepted
-
2019-05-22: Public meeting
-
2019-06-28: ALJ report issued
-
: Permit Decision
-
: Project built
-
: Project Closed
|
15-858 | | Minnesota Energy Resources Corporation is proposing to install approximately 13.1 miles of new natural gas pipeline west and south of the city of Rochester in Olmsted County, Minnesota | 11/03/2015 12:00 AM |
View All...
-
2016-02-03: Application accepted
-
2016-02-29: Public meeting
-
2016-07-26: Routes accepted for consideration
-
2016-09-16: Environmental document available
-
Upcoming: Public hearing
-
Upcoming: Permit issued
-
Upcoming: Project built
-
Upcoming: Docket closed
|
15-137 | | Enbridge Energy proposes to replace 337 miles of the Line 3 Pipeline in Minnesota. Line 3 originates in Canada, continues through North Dakota, enters Minnesota in Kittson County, and terminates in Superior, Wiscsonsin. | 02/23/2015 12:00 AM |
View All...
-
2015-07-01: Application accepted
-
2016-04-25: Public meeting
-
2016-12-05: Scoping decision
-
2017-05-15: Draft EIS available
-
2017-09-26: Public hearing
-
2018-02-02: Final EIS available
-
2018-04-24: ALJ report issued
-
2018-10-26: Permit issued
-
Upcoming: Project built
-
Upcoming: Docket closed
|